The Dugopolje-Peruća pipeline route will start at the existing pipeline intersection in Koprivno near Dugopolje, on the Bosiljevo-Split trunkline. The terminal point of the pipeline will near the Peruća CCNGT, at the new Peruća Station.
The Dugopolje-Peruća pipeline route will start at the existing pipeline intersection in Koprivno near Dugopolje, on the Bosiljevo-Split trunkline. The terminal point of the pipeline will near the Peruća CCNGT, at the new Peruća Station.
Natural gas delivery to Peruća CCNGPP
Length of 24-kilometer, starting at Koprivno pipeline intersection near Dugopolje, ending at the new Peruća station
Nominal diameter of pipeline is DN 500, nominal pressure is 75 bar
All monitoring and management equipment and installations, as well as security devices, will be connected to the National Dispatch Centre in Plinacro, Zagreb
The planned service life of the pipeline is estimated at 50 years of its operation, test operation of the pipeline will last up to one year
Due to distances greater than 1,000 meters and underground pipes, the pipeline will have no impact on the ecological network’s conservation objectives